UNDP RSS
General Information
Focus Area CPR and Peacebuilding
Geographic
Coverage
North
Project Status Ongoing
Start Date 01 December 2007
Expected End Date 01 December 2011

MDG Goal
1. Eradicate extreme poverty and hunger
MYFF 2004-2007 Goal
4. Crisis prevention and recovery
MYFF Service Line
2. Recovery
SRF 2006 Outcome
8. Conflict prevention and peace-building approaches informed/factored into national/local development frameworks, and integrated programmes designed and implemented at national and local level

Executing Agency
UNDP (Direct Execution) (UNDP)
Implementing Partners
UNDP (Direct Execution) (UNDP)

Projects Database / Coordinated support to UNRWA in response to Naher El Bared Crisis

Project ID
00056998


Background
On May 20th, 2007, fierce clashes erupted between armed members of the radical group Fatah Al Islam (FAI) and the Lebanese Army, in Tripoli in Northern Lebanon. These clashes took place in the Palestinian refugee camp of Nahr El Bared (NBC), infiltrated by around 200 armed FAI fighters.
The strategy adopted since the beginning of the crisis consists of providing coordinated support to UNRWA, the mandated lead agency for Palestinian refugees. Support is ensured by the Resident Coordinator (RC) and the United Nations Country Team, through the cluster and inter-cluster meetings organized and led by the different UN agencies, with the participation of NGOs and Civil Society Organizations.
UNDP will support national capacities of the HRC (GIS-based data management system) and the Lebanese Palestinian Dialogue Committee (LPDC), including additional human resources, equipment and the provision of satellite images. UNDP, through its support to the NDO, is also arranging for MAG to carry out demining activities immediately upon cessation of hostilities. UNDP will also provide technical support to UNRWA on the temporary electricity repairs.

Achievements & Expected Results
These funds are to be utilized in support of UNRWA overall coordination efforts, namely:

Output 1. Coordinated support to the government in response to Nahr El bared Camp Crisis

Activities:

1.1. Recruitment of a Relief and Reconstruction Officer,
1.2. Purchase of a MOSS compliant car to support the Lebanese-Palestinian Dialogue Committee

Output 2. Support to the production assessment satellite images established and shared with stakeholders and public at large.

Activities:

2.1 Production of 4 satellite images
2.2 Production of 2 comparative damage assessments based on the satellite images

Output 3. Technical advice to temporary electricity repairs in NBC provided

3.1. A mission from an internal expert on electricity in crisis settings



Downloads

N/A

Relevant News

N/A

Expenditures
2010 $250,000.00  
Total $250,000.00  

Target Groups/Beneficiaries
Vulnerable Groups

Contact Information
Project Manager: N/A
UNDP Portfolio Manager: Celine Moyroud
UNDP Project Manager: Celine Moyroud
Address: UNDP Country Office, Arab African International Bank Building Riad El Solh Street, Nejmeh, Beirut 2011 5211 Lebanon
Fax: +961 985 932

Last Updated
16 March 2010